Stay up to date with notifications from The Independent

Notifications can be managed in browser preferences.

Heathrow’s third runway: The big questions, answered

The decision is in, but the battle is far from over. Our travel correspondent Simon Calder provides a guide to what happens next

Simon Calder
Tuesday 25 October 2016 18:54 BST
Comments
It could be many years before building begins on Heathrow’s third runway
It could be many years before building begins on Heathrow’s third runway (AFP/Getty Images)

Your support helps us to tell the story

From reproductive rights to climate change to Big Tech, The Independent is on the ground when the story is developing. Whether it's investigating the financials of Elon Musk's pro-Trump PAC or producing our latest documentary, 'The A Word', which shines a light on the American women fighting for reproductive rights, we know how important it is to parse out the facts from the messaging.

At such a critical moment in US history, we need reporters on the ground. Your donation allows us to keep sending journalists to speak to both sides of the story.

The Independent is trusted by Americans across the entire political spectrum. And unlike many other quality news outlets, we choose not to lock Americans out of our reporting and analysis with paywalls. We believe quality journalism should be available to everyone, paid for by those who can afford it.

Your support makes all the difference.

Between now and the prospective opening of a new runway at Heathrow at some time between 2025 and 2030, the great airport debate will continue even more noisily. Here are the key questions and their answers.

When do the bulldozers move in?

Certainly not in the year ahead, when a public consultation will take place. Expansion at Heathrow will then be put to parliamentary vote. Only then can the planning process properly begin. Work to flatten much of the village of Harmondsworth is unlikely to start before 2020. But much could happen between now and breaking ground.

Assuming the Government wins support from a majority of MPs, can it simply push the project through?

The Government will certainly demand faster progress than Terminal 5 at Heathrow, which took about 20 years between the submission of the planning application and the opening. But four local authorities that oppose expansion, together with the environmental group, Greenpeace, will mount challenges in the High Court that could derail the proposal. There are a range of issues on which they might seek a judicial review of the decision, with the most likely candidates increased air pollution and noise.

If there is no successful challenge, and as expected the parliamentary vote supports Heathrow, then the Government will issue a National Policy Statement and invite Heathrow to begin the planning process. That in turn could be challenged legally. But if it proceeds smoothly, the new runway could conceivably be ready by 2025 — though the associated works, particularly on a new Terminal 6, could take several years longer.

Will the number of flights increase the moment the runway opens?

No. How the growth from 480,000 movements a year to 740,000 is handled is one of the key questions that has not been properly addressed. Airlines will simply not countenance being asked to expand their operation by 50 per cent overnight. Instead, it may be that operations at Heathrow are gradually increased with the use of “mixed mode” — landings and take-offs from both runways, simultaneously. That could add around 15 per cent of capacity, to 550,000 a year, though it would be extremely politically contentious. Instead, Northolt (a military airfield to the north of Heathrow) could be used for some short-haul links with road connection between the two.

Flybe, the UK’s largest regional airline, says: “The Government should allow scheduled commercial flights to and from RAF Northolt to fast-track the benefits of regional connectivity. The new capacity at Heathrow will take a decade or more to build and Northolt is available right now.”

Another option is to persuade airlines to start new services from Luton or Stansted with the promise of guaranteed slots at Heathrow when work is complete.

Assuming it goes ahead, will the new runway guarantee connectivity to more cities in the UK and “emerging markets”?

One of the sweeteners offered by all three of the shortlisted projects is significantly to increase the range of destinations served in the UK, with airports such as Liverpool, City of Derry and Dundee holding out the hope of links with the expanded airport. It is likely that the policy statement will demand slots “ring-fenced” for services to and from regional airports.

Flybe has demanded that some of the new capacity should be “reserved for operators of regional aircraft at affordable prices”.

Links to overseas destinations, though, cannot be prescribed by Government. Instead, airlines will decide where to fly. Just this week, British Airways has cancelled its link from Heathrow to Chengdu in western China (an archetypal emerging market), and replaced it with flights to New Orleans.

Will fares rise or fall?

The short answer is: no one knows. Heathrow’s third runway is by far the most expensive option of the three on the shortlist, with a current price tag of £17.6bn. The short-term question is: should current passengers pay for future development? That practice is common at a number of airports which levy a “development fee” on all passengers.

Airlines are firmly against that prospect, and are demanding that Heathrow’s charges are capped at the present level. But deferring the airport’s reward for expansion would involve Heathrow taking on a vast amount of debt which, if charges were constrained, could take decades to pay back. So there is likely to be some kind of compromise, which may allow for a modest increase in charges during the construction.

Once the new runway is up and running, the number of passengers should soar, providing much more revenue for Heathrow.

If low-cost airlines such as easyJet, and the long-haul operators Norwegian and WestJet, are able to compete with incumbent carriers, fares should fall, even allowing for extra charges.

Are Gatwick’s plans now in tatters?

Not according to Stewart Wingate, the Chief Executive of the Sussex airport. “If the Government needs to call on us, then they can. I personally don’t think another runway will be delivered at Heathrow in my lifetime. Heathrow’s been in this situation twice before.” However, he conceded that Gatwick would need Government support through the planning process.

Join our commenting forum

Join thought-provoking conversations, follow other Independent readers and see their replies

Comments

Thank you for registering

Please refresh the page or navigate to another page on the site to be automatically logged inPlease refresh your browser to be logged in