Steps to project's go-ahead: Sellafield
Your support helps us to tell the story
From reproductive rights to climate change to Big Tech, The Independent is on the ground when the story is developing. Whether it's investigating the financials of Elon Musk's pro-Trump PAC or producing our latest documentary, 'The A Word', which shines a light on the American women fighting for reproductive rights, we know how important it is to parse out the facts from the messaging.
At such a critical moment in US history, we need reporters on the ground. Your donation allows us to keep sending journalists to speak to both sides of the story.
The Independent is trusted by Americans across the entire political spectrum. And unlike many other quality news outlets, we choose not to lock Americans out of our reporting and analysis with paywalls. We believe quality journalism should be available to everyone, paid for by those who can afford it.
Your support makes all the difference.1946: Sellafield chosen as plutonium production site for UK's nuclear weapons programme.
1952: Radioactive discharges to the Irish Sea begin.
1956: The Queen opens Calder Hall nuclear power station.
1957: One of two 'Windscale Piles', military plutonium production reactors, catches fire.
1964: Reprocessing of fuel from civil Magnox reactors begins.
1971: British Nuclear Fuels Ltd is hived off from the UK Atomic Energy Authority.
1973: Explosion in the 'Head End Plant' contaminates building B204.
1975: BNFL approaches Tony Benn, then Secretary of State for Energy, about building the Thermal Oxide Reprocessing Plant to replace the B204.
1976: Major radioactive leak at Windscale. Cumbria County Council approves Thorp.
1977: Windscale planning inquiry under Mr Justice Parker.
1978: Mr Justice Parker reports and approves the plant. Commons gives approval. 1979: Three Mile Island accident.
1981: Name is changed from Windscale to Sellafield.
1983: Work begins on facilities for spent fuel.
1985: Construction work begins on Thorp.
1986: Chernobyl accident.
1992 February: Thorp completed at a cost of pounds 1.85bn - pounds 1.9bn has been paid in advance by overseas customers. BNFL build pollution treatment plant costing more than pounds 1bn.
1992 November: Public consultations on Thorp.
1993 August: Second two-month period of public consultation opens.
1993, 15 December: Government gives plant go-ahead. Greenpeace and Friends of the Earth mount legal challenges.