National Highways projects costing billions more than planned
The National Audit Office said delays and inflation mean National Highways will not be able to deliver dozens of projects within budget.
Your support helps us to tell the story
From reproductive rights to climate change to Big Tech, The Independent is on the ground when the story is developing. Whether it's investigating the financials of Elon Musk's pro-Trump PAC or producing our latest documentary, 'The A Word', which shines a light on the American women fighting for reproductive rights, we know how important it is to parse out the facts from the messaging.
At such a critical moment in US history, we need reporters on the ground. Your donation allows us to keep sending journalists to speak to both sides of the story.
The Independent is trusted by Americans across the entire political spectrum. And unlike many other quality news outlets, we choose not to lock Americans out of our reporting and analysis with paywalls. We believe quality journalism should be available to everyone, paid for by those who can afford it.
Your support makes all the difference.Enhancements to Englandās motorways and major A roads will cost billions of pounds more than planned, a report has found.
Public spending watchdog the National Audit Office (NAO) said delays and inflation mean Government-owned company National Highways will not be able to deliver dozens of projects within budget.
The report warned it will cost an estimated Ā£3.3 billion more than planned to complete projects due to take place in the second road investment strategy (RIS2) between April 2020 and March 2025.
It also stated that projects due to be in construction during the subsequent five years are likely to cost Ā£6 billion above previous expectations, although that includes some of the schemes included in the Ā£3.3 billion figure.
Some 33 schemes are behind schedule by between one month and more than three years, with an average delay of 12 months.
āThis will leave road users with an underperforming road network for longer,ā the report warned.
Delays have been caused by factors such as the coronavirus pandemic and difficulties obtaining planning permission.
National Highways was given a total of Ā£14.1 billion by the Department for Transport (DfT) for 69 enhancement schemes in RIS2.
It has completed less work and at a higher cost than anticipated, the NAO said.
Projects in RIS2 include building a dual carriage and tunnel near Stonehenge, Wiltshire and the Lower Thames Crossing between Kent and Essex.
Neither have received development consent.
Last year, the budget for enhancements was cut by Ā£3.4 billion and the number of projects were reduced to 58 when it became clear National Highways could not implement the delivery plan as intended.
The NAO also found that National Highways has already allocated all of its Ā£1.16 billion RIS2 contingency budget.
Gareth Davies, head of the NAO, said it was āunfortunateā that the road investment plan developed by the DfT and National Highways coincided with the coronavirus pandemic and rising inflation, but āmore could have been done to manage risksā.
He went on: āDelays to projects have meant that less work has been delivered than planned and at a higher cost.
āDfT and National Highways must now fully address the rising cost of its revised portfolio of projects, undertaking a review of all road plans that it plans to move into the time period of its third road strategy (2025-2030).
āThis review must consider if these projects remain feasible and provide optimal value for money.ā
National Highways chief executive Nick Harris said, āexternal factorsā have had a āsignificant impact on our ability to deliver this complex programmeā.
He continued: āDespite these challenges, we have successfully received consent to deliver several major infrastructure developments.
āWeāre confident that we manage portfolio and project risks well, while recognising that there is always room for improvement as we mature our processes ready for RIS3.ā
A DfT spokesman said RIS2 is ātransforming our road networkā and a āminority of projectsā are being delivered later than originally proposed.
He added: āWe have allocated Ā£24 billion to ensure we have a road network that is safe, reliable, environmentally conscious and good value for the taxpayer.ā
RAC head of roads policy Nicholas Lyes said drivers will be āvery frustrated if vital improvement works are put on holdā.
He went on: āAny attempts to take an axe to the roads budget is short-sighted because slow-moving traffic and delays do nothing to help the economy grow.ā