HS2 rated ‘unachievable’ by major projects body
A red rating, in an Infrastructure and Projects Authority report, states: ‘Successful delivery of the project appears to be unachievable.’
Your support helps us to tell the story
From reproductive rights to climate change to Big Tech, The Independent is on the ground when the story is developing. Whether it's investigating the financials of Elon Musk's pro-Trump PAC or producing our latest documentary, 'The A Word', which shines a light on the American women fighting for reproductive rights, we know how important it is to parse out the facts from the messaging.
At such a critical moment in US history, we need reporters on the ground. Your donation allows us to keep sending journalists to speak to both sides of the story.
The Independent is trusted by Americans across the entire political spectrum. And unlike many other quality news outlets, we choose not to lock Americans out of our reporting and analysis with paywalls. We believe quality journalism should be available to everyone, paid for by those who can afford it.
Your support makes all the difference.The HS2 programme has been given an “unachievable” rating by the official infrastructure watchdog.
A “red” rating was assigned to the plans for the construction of the first two phases of the troubled rail line, from London to Birmingham and then on to Crewe in Cheshire, by the Infrastructure and Projects Authority (IPA).
The red rating, contained in the IPA’s annual report on major projects – which was released last week, states: “Successful delivery of the project appears to be unachievable.
“There are major issues with project definition, schedule, budget, quality and/or benefits delivery, which at this stage do not appear to be manageable or resolvable.
“The project may need re-scoping and/or its overall viability reassessed.”
Earlier this month, HS2 Ltd’s chief executive Mark Thurston, 56, announced his resignation amid major delays and cost pressures for the high-speed railway project.
He is to leave his role in September after six-and-a-half years leading the Government-owned company.
HS2 was initially scheduled to open in 2026, but this has been delayed to between 2029 and 2033 due to construction difficulties and rising costs.
A budget of £55.7 billion for the whole project was set in 2015, but the target cost excluding the eastern leg of Phase 2b from the West Midlands to the East Midlands has soared to between £53 billion and £61 billion at 2019 prices.
In March, Transport Secretary Mark Harper announced work at Euston would be paused for two years as costs had ballooned to £4.8 billion compared with an initial budget of £2.6 billion.
Mr Thurston’s resignation announcement came while Phase One of the project between London and Birmingham is at peak construction, with major work taking place at more than 350 sites.
The IPA is the Government’s centre of expertise for infrastructure and major projects. It sits at the heart of government and reports to the Cabinet Office and HM Treasury.
A Department for Transport spokesman said: “Spades are already in the ground on HS2, with 350 construction sites, over £20 billion invested to date and supporting over 28,500 jobs.
“We remain committed to delivering HS2 in the most cost-effective way for taxpayers.
“HS2 will bring transformational benefits for generations to come, improving connections and helping grow the economy.”