Fukushima nuclear plant operator says equipment to release treated wastewater into sea is complete

Officials say all equipment needed for the release into the sea of treated radioactive wastewater from the wrecked Fukushima nuclear plant has been completed and will be ready for an inspection by Japanese regulators this week

Mari Yamaguchi
Monday 26 June 2023 13:15 BST

Your support helps us to tell the story

From reproductive rights to climate change to Big Tech, The Independent is on the ground when the story is developing. Whether it's investigating the financials of Elon Musk's pro-Trump PAC or producing our latest documentary, 'The A Word', which shines a light on the American women fighting for reproductive rights, we know how important it is to parse out the facts from the messaging.

At such a critical moment in US history, we need reporters on the ground. Your donation allows us to keep sending journalists to speak to both sides of the story.

The Independent is trusted by Americans across the entire political spectrum. And unlike many other quality news outlets, we choose not to lock Americans out of our reporting and analysis with paywalls. We believe quality journalism should be available to everyone, paid for by those who can afford it.

Your support makes all the difference.

All equipment needed for the release into the sea of treated radioactive wastewater from the wrecked Fukushima nuclear plant has been completed and will be ready for a safety inspection by Japanese regulators this week, the plant operator said Monday, as opposition to the plan continues in and outside Japan over safety concerns.

Tokyo Electric Power Company Holdings said it installed the last piece of an undersea tunnel dug to release the water offshore, completing the construction of the necessary equipment that began last August.

A mandatory safety inspection of the equipment will begin Wednesday, said Nuclear Regulation Authority Chairman Shinichi Yamanaka, who visited the Fukushima Daiichi plant last week.

If everything goes well, TEPCO is expected to receive a safety permit for the release about a week after the inspection ends, officials said. Discharge of the treated water is expected to begin this summer, although the exact date has not been set.

The plan has faced fierce protests from local fishing groups concerned about safety and reputational damage. Nearby countries, including South Korea, China and some Pacific Island nations, have also raised safety concerns.

Government and utility officials say the wastewater, currently stored in about a thousand tanks at the plant, must be removed to prevent any accidental leak in case of an earthquake and to make room for the plant’s decommissioning. They say the treated but still slightly radioactive water will be diluted to safe levels and will be released gradually into the ocean over decades, making it harmless to people and marine life.

Some scientists say the impact of long-term, low-dose exposure to radionuclides is unknown and the release should be delayed. Others say the release plan is safe but call for more transparency, including allowing outside scientists to join in sampling and monitoring the release.

Japan has sought support from the International Atomic Energy Agency to gain credibility and ensure that safety measures meet international standards.

A massive earthquake and tsunami on March 11, 2011, destroyed the Fukushima Daiichi nuclear plant’s cooling systems, causing three reactors to melt and their cooling water to be contaminated and leak continuously. The water is collected, treated and stored in the tanks, which will reach their capacity in early 2024.