Stay up to date with notifications from The Independent

Notifications can be managed in browser preferences.

Company says manufacturing problem was behind wind turbine blade breaking off Nantucket Island

The maker of a massive wind turbine blade that broke apart off Nantucket Island says a manufacturing problem was responsible

Via AP news wire
Thursday 25 July 2024 21:28 BST
Nantucket Wind Turbine Damaged
Nantucket Wind Turbine Damaged (Copyright 2023 The Associated Press. All rights reserved.)

Your support helps us to tell the story

As your White House correspondent, I ask the tough questions and seek the answers that matter.

Your support enables me to be in the room, pressing for transparency and accountability. Without your contributions, we wouldn't have the resources to challenge those in power.

Your donation makes it possible for us to keep doing this important work, keeping you informed every step of the way to the November election

Head shot of Andrew Feinberg

Andrew Feinberg

White House Correspondent

The maker of a massive wind turbine blade that broke apart off Nantucket Island and washed up on the beaches says a manufacturing problem was responsible.

GE Vernova CEO Scott Strazik said on an earnings call Wednesday that insufficient bonding at one of its factories in Canada was responsible for the blade coming apart and that there was no indication of a design flaw. As a result, the company will reinspect all 150 blades that had been made at the factory.

“To identify deviations, we are going to go and do this on every blade. Prudent, thorough process,” he told the call. “We’re not going to talk about the timeline today. We have work to do. But I have a high degree of confidence that we can do this.”

Parts of the blade, which is more than 100 meters (109 yards) long, began to fall into the ocean July 13 at the Vineyard Wind project and crews in boats and on beaches have been collecting truckloads of debris ever since. The company said that the debris consists of nontoxic fiberglass fragments and that any washing ashore are pieces of one square foot or less.

The federal Bureau of Safety and Environmental Enforcement said last week that operations at Vineyard Wind have been suspended until it can be determined whether the “blade failure” impacts other turbine blades on the development.

“As GE Vernova continues the investigation into the root cause of the damage to its blade, Vineyard Wind 1 remains focused on coordinating with the Bureau of Safety and Environmental Enforcement, assisting in the recovery of debris, and prioritizing the safety of personnel, local communities, and the environment,” Craig Gilvarg, a company spokesman, said in a statement.

Vineyard Wind is a joint venture between Avangrid and Copenhagen Infrastructure Partners and said no personnel or third parties were near the turbine when the damage occurred. It said in a statement that blade manufacturer and installation contractor GE “will now be conducting the analysis into the root cause of the incident.”

The development’s massive wind turbines began sending electricity to the grid this past winter. It said it will deploy trained individuals to collect the debris for the next several days

Thank you for registering

Please refresh the page or navigate to another page on the site to be automatically logged inPlease refresh your browser to be logged in