Hinkley Point C nuclear plant ‘could cost up to £35 billion’

EDF is aiming for HPC to become a major source of decarbonised electricity supply for the UK, providing around 7% of national consumption

Helen William
Tuesday 23 January 2024 21:28 GMT
Work at Hinkley Point C (EDF)
Work at Hinkley Point C (EDF) (PA Media)

Your support helps us to tell the story

From reproductive rights to climate change to Big Tech, The Independent is on the ground when the story is developing. Whether it's investigating the financials of Elon Musk's pro-Trump PAC or producing our latest documentary, 'The A Word', which shines a light on the American women fighting for reproductive rights, we know how important it is to parse out the facts from the messaging.

At such a critical moment in US history, we need reporters on the ground. Your donation allows us to keep sending journalists to speak to both sides of the story.

The Independent is trusted by Americans across the entire political spectrum. And unlike many other quality news outlets, we choose not to lock Americans out of our reporting and analysis with paywalls. We believe quality journalism should be available to everyone, paid for by those who can afford it.

Your support makes all the difference.

The final cost of the Hinkley Point C nuclear plant, being built in Somerset, could be as much as £35 billion, according to the French firm developing it.

The start of electricity production had been scheduled for June 2027 – but the completion date could now be up to three years later, energy giant EDF said.

A re-evaluation of the schedule and cost estimates, which have been expressed in 2015 prices, suggests that one of the two planned reactors in Somerset could be ready in 2029.

Another evaluation assumes it could be operational a year later, while a final scenario suggests adverse conditions could see that drag on until 2031, EDF warned.

The bill for completing the project is now estimated at between £31-34 billion in 2015 values.

The firm said if the risk of an additional 12-month delay – as imagined in the final scenario – did happen, it would result in an estimated additional cost of around £1 billion in 2015 values.

EDF is aiming for HPC to become a major source of decarbonised electricity supply for the UK, providing around 7% of national consumption.

In a note to Hinkley project staff, Stuart Crooks, managing director of Hinkley Point C (HPC), said: “Like other infrastructure projects, we have found civil construction slower than we hoped and faced inflation, labour and material shortages – on top of Covid and Brexit disruption.”

In December last year, building work on the multibillion-pound nuclear power station reached a major milestone, with the first reactor building being lifted into place.

EDF said the achievement ended the year on a high as the 14m-tall dome sat on top of the reactor building, which is 44 metres high.

It was said that around 10,000 workers and 3,500 British companies were involved in the building Hinkley Point C.