Developer to demolish and rebuild 84 homes due to problems with foundations

The foundations of the newly built homes were found to be insufficient

Sam Russell
Tuesday 26 September 2023 11:47 BST
Some new homes will have to be demolished (David Davies/PA)
Some new homes will have to be demolished (David Davies/PA) (PA Archive)

Your support helps us to tell the story

From reproductive rights to climate change to Big Tech, The Independent is on the ground when the story is developing. Whether it's investigating the financials of Elon Musk's pro-Trump PAC or producing our latest documentary, 'The A Word', which shines a light on the American women fighting for reproductive rights, we know how important it is to parse out the facts from the messaging.

At such a critical moment in US history, we need reporters on the ground. Your donation allows us to keep sending journalists to speak to both sides of the story.

The Independent is trusted by Americans across the entire political spectrum. And unlike many other quality news outlets, we choose not to lock Americans out of our reporting and analysis with paywalls. We believe quality journalism should be available to everyone, paid for by those who can afford it.

Your support makes all the difference.

A developer is to demolish and rebuild more than 80 new homes due to problems with their foundations.

Darwin Green, less than two miles from Cambridge city centre, is still under construction and has outline approval for 1,593 new homes.

In June, developers Barratt and David Wilson said they had “discovered issues with the design of some of the foundations” of some homes under construction on phase two of the estate.

They said in a letter to residents at the time that the foundations of 84 “incomplete and unoccupied” homes “were found to be insufficient given the geology of the next phase”.

Initially, they said that 30 homes would need to be demolished and rebuilt, and the remaining plots would “also require work to remove the foundations and any other structures that have been started”.

In documents submitted to Cambridge City Council this month, the developers said that “circa 83 units” would need to be demolished.

In the letter to residents in June, the developers said that “some of the properties which require demolition had been reserved by our customers”.

“We have met with all of the customers whose homes are affected on Phase Two and have offered them a range of options and support,” they said.

“We are pleased that many have decided to continue with their purchase of a new home at Darwin Green.”

We sincerely apologise for any negative impact this situation may have on you and we are fully committed to minimising any impact of the remedial work as much as we possibly can

Barratt David Wilson Cambridgeshire

The letter, from Barratt David Wilson Cambridgeshire, added: “We sincerely apologise for any negative impact this situation may have on you and we are fully committed to minimising any impact of the remedial work as much as we possibly can.”

The developer said it had been working with the local authority and its demolition contractor to prepare a plan which has “as little impact on existing residents and the wider environment and community as possible”.

Demolition proposals have now been submitted to the local authority and are awaiting a planning decision.