MPs launch inquiry into £4bn Palace of Westminster renovation plan
Concerns over proposals prompt select committee investigation – but some MPs demand even more expensive option
Your support helps us to tell the story
This election is still a dead heat, according to most polls. In a fight with such wafer-thin margins, we need reporters on the ground talking to the people Trump and Harris are courting. Your support allows us to keep sending journalists to the story.
The Independent is trusted by 27 million Americans from across the entire political spectrum every month. Unlike many other quality news outlets, we choose not to lock you out of our reporting and analysis with paywalls. But quality journalism must still be paid for.
Help us keep bring these critical stories to light. Your support makes all the difference.
Multi-billion pound plans to renovate the Houses of Parliament are to be investigated by a committee of MPs amid growing concern about the cost of the project.
The chairman of the House of Commons Treasury Select Committee, Andrew Tyrie, says there is not enough evidence to justify the estimated costs of up to £4 billion.
The Palace of Westminster is said to be in urgent need of major maintenance work. Under proposals to be debated by the House of Commons later this month, MPs and peers would have to move out of the building for up to eight years while the work is completed.
“The restoration and renewal programme is estimated to cost between £3.5 and £4bn over five to eight years,” Mr Tyrie said.
“Neither the report by Deloitte nor that by the joint commission provides enough of the evidence needed to come even to a preliminary decision on these proposals.
“So the Treasury Committee will attempt to collect some of it. This is why the committee has called for evidence on this massive, and hugely expensive, restoration project. The proposals certainly need thorough scrutiny.”
Officials have previously concluded the Palace is at risk of a “catastrophic failure” such as a flood or fire because plumbing and electrical infrastructure is “no longer fit for purpose”.
Work is needed to install new piping and cabling, repair crumbling stonework, remove asbestos, restore 4,000 windows and repair damaged roofs.
Under some proposals, MPs and peers would be allowed to continue to use the Palace for debates while the work is carried out. This carries a much larger price tag of up to £7 billion. The Treasury Select Committee will look at whether a plan to carry out the work over a longer period could cause less disruption.
Last week a cross-party group of MPs backed the alternative plan that would allow MPs to stay in the Palace of Westminster and establish two temporary debating chambers elsewhere in the building.
Edward Leigh, Conservative MP for Gainsborough, told the Architects’ Journal: “The Houses of Parliament are an iconic symbol of our parliamentary democracy. To abandon it at one of the most critical junctures in our history is senseless.
“Wasting money to build a permanent new chamber that will only temporarily house the Commons is pure folly. In this time of austerity it’s unjustifiable, and we intend to keep a close eye on the costs involved in this project.”
Architects have suggested the House of Commons could meet in the Lords Chamber while the House of Lords relocates to the Royal Gallery, which is currently used for banquets and state receptions.
Under the current plans to temporarily move Parliament while the restoration work is carried out, MPs would be housed in a space in the Department of Health offices, while the Lords would set up a chamber at the Queen Elizabeth II Conference Centre in Westminster.
Subscribe to Independent Premium to bookmark this article
Want to bookmark your favourite articles and stories to read or reference later? Start your Independent Premium subscription today.
Join our commenting forum
Join thought-provoking conversations, follow other Independent readers and see their replies
Comments